Fengmiao Offshore Wind Power Co., Ltd. is handling the "Taichung Fengmiao Wind Power Project Phase I" application.
A -
A -
A +
Release date:
2026-02-04
| View count:
136
| Maintenance unit:
Central Taiwan Maritime Affairs Center
| Last Verify Time:
2026-02-04
| Last Modified:
2026-02-04
The deployment period for marine meteorological buoys under this plan is from F
ebruary 5, 2026 to December 31, 2027; the protection zone for escort vessels is fr
om February 9, 2026 to December 31, 2026; and the installation area for submarin
e cables is from March 1, 2026 to August 31, 2026. The actual project duration m
ay be adjusted based on weather conditions and project progress.
Vessels navigating this area are advised to avoid it and exercise caution during na
vigation.
download attachment:
海氣象浮標布放期限為115 年2 月5 日開始至116 年12 月31 日
.pdf
戒護船戒護區域期限為115 年2 月9 日開至115 年12 月31 日
.pdf
輸出海纜安裝區域115 年3 月1 日開始115 年8 月31 日
.pdf
MOTC_26-54
.pdf
-
-
礙航公告(中區)(至116年12月31日)渢妙離岸風力發電股份有限公司辦理「台中渢妙風力發電計畫第一期」海氣象浮標布放、戒護船戒護區域、輸出海纜安裝區域 (1)